iLab U.S. Server Migration Friday, June 18th, 2021 21:00:00 EDT


On Friday June 18th, 2021 at 9:00 PM (EST), Agilent Site Reliability Engineers will be migrating the following server nodes onto the Agilent Amazon Web Services (AWS) infrastructure.

  • iLab Primary US instance
  • iLab DFCI instance
  • iLab Catalog Database instance

This migration will improve performance across the US sites and increase efficiency, as well as be more secure than the previous instance. Migration is expected for 8 hours, and during this time, iLab sites on the US server will be unavailable.

[Friday June 18th; 9:05 PM (EST)] - Migration process has begun and iLab services on US server instance are now unavailable .

[Friday June 18th; 9:09 PM (EST)] - Agilent Engineers have stopped the web and job services.

[Friday June 18th; 9:30 PM (EST)] - Backup and restore on servers has begun.

[Friday June 18th; 10:37 PM (EST)] - Restore complete. API deploy has started.

[Friday June 18th; 11:18 PM (EST)] - Services for iLab Primary US sites are available. Catalog Database features are still unavailable.

[Friday June 18th; 11:20 PM (EST)] - Migration on Catalog Database has started.

[Saturday June 19th; 12:11 AM (EST)] - Services restarted on Catalog Database instance and migration complete.

[Saturday June 19th; 12:14 AM (EST)] - Migration on DFCI instance has started.

[Saturday June 19th; 12:17 AM (EST)] - Backup on DFCI instance has started.

[Saturday June 19th; 12:34 AM (EST)] - Backup on DFCI instance complete.

[Saturday June 19th; 12:49 AM (EST)] - Migration complete on DFCI instance and site is available.

[Saturday June 19th; 1:10 AM (EST)] - Migration complete, and all sites operational.

Please contact iLab Support at ilab-support@agilent.com, with any questions or concerns.